326ISEV : Computer Project Management Assignment 1
Meeting Minutes - 1st April 2008
Opening:
The regular meeting of the Project Management Team was called to discuss the project of re-locating of GetItFast Limited. We met in the computer room during the Easter break.
Present: Jon Tolin and Emma Ryan
Apols: Ayman Adly and Hayden Webb
Agenda…..
1. Look at what is left to complete Part 1/Section 1 of the project assignment.
2. Assign tasks to complete Part 1/Section 1
Minutes of meeting…..
-
Jon and Emma looked at what the group needs to do to complete Part 1/Section 1 of the group project.
The specification was broken down into areas and looked at what had already been completed and what is still to be completed (TBC) as follows:-
| Completed? | Code | Description | Notes |
| Hayden | A | Description and scope of Project | How it is going to be run |
| Hayden | B | List of stakeholders and their involvement | What we are doing and what we are not doing |
| TBC | C | Statement of requirements | What GetItFast requirements are |
| TBC | D | Resources Required | What will be needed? People and things that would be needed |
| TBC | E | Project Management roles and responsibilities | What are the people going to do? |
| TBC | F | Project Deliverables | Anything that comes out of a task (A Thing) |
| Jon | G | Work Breakdown Structure | Breakdown of Work to be completed |
| TBC | H | Risk Analysis | What Risks are there? |
| TBC | J | Collate Document | Collate all A-H in one document. |
2. The parts of the specification that were still TBC were discussed and allocated to members of the team to look at and write up before the next meeting on 10th April.
The following was then decided: (See the table below and the text beneath the table explains the reasoning of this and further details)
| Completed? | Code | Description | Notes |
| Hayden | C | Statement of requirements | What GetItFast requirements are |
| Ayman | D | Resources Required | What will be needed? People and things that would be needed |
| Emma | E | Project Management roles and responsibilities | What are the people going to do? |
| Jon | F | Project Deliverables | Anything that comes out of a task (A Thing) |
| All | H | Risk Analysis | What Risks are there? |
| Emma | J | Collate Document | Collate all A-H in one document. |
Emma would collate the work completed so far (J Collate Document) and the areas C, D, E, F and H were allocated as above, see below for further information. (These items are to be fed back to the group ready for the next meeting).
C - Statement of requirements
This was allocated to Hayden as it is related to the Description and scope of Project and List of stakeholders and their involvement he has already completed (A&B).
D - Resources Required
As Ayman is the man who can it was thought that he could decide what resources would be required. i.e. equipment and people
E - Project Management roles and responsibilities
Emma will look into the roles and responsibilities of the group and what the roles of the people within the project will be doing,
F - Project Deliverables
As the Project Deliverables is part of the WBS (Work Breakdown Structure - G) it was decided Jon would be best to complete this part of the assignment as he constructed the WBS. He is to decide anything to come out of a task as this is a project deliverable.
H - Risk Analysis
This can really only be completed once the tasks (Project Deliverables) have been completed. It was decided that all members of the group would look at the risks and discuss this at the next meeting.
J - Collate Document
As Emma is the administrator of the group she would collate the document as and when tasks are completed.
All tasks that are to be completed need to be fed back to the group ready for the next meeting. This can be done either by email or by uploading information to the blog.
Next Meeting…..
The next meeting will be after class on 10th April 2008, location to be decided.
Agenda for Next Meeting….
The agenda for next meeting will be as follows:-
-
Review project so far and ensure that all of Part 1/Section 1 is complete.
-
Evaluate the risks and compile a risk analysis as a group or delegate this task to one member of the group.
-
Discuss Part 2/Section 2, assign tasks as necessary.
Minutes submitted by: Emma Ryan
Approved by: Ayman Adly, Hayden Webb, Jon Tolin
Page 1 of 4